A.  Acceptance and approval of Change Order No. 6 for additional 38 days due to adverse weather for Contract No. C-14-067-06-03 with JCon Construction, LLC as reviewed/approved by project architect of record, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of the Linn-San Manuel Emergency Services Facilities" with authority for County Judge, or Court Member to execute document. 

B.  Acceptance and approval of request for payment of invoice 15-4-000012 submitted by L&G Engineering Laboratory for the Linn San Manuel Facility (PO# 713423).

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2015
ACCT. #:
5-1301-419-40-124-136-0-720
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO# 713423 -L&G ENGINEERING

FISCAL YEAR:
2015
ACCT. #:
5-1301-419-40-124-136-0-730
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

PO#712761
Change order has no fiscal impact.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 05/01/2015 09:33 AM
Budget and Management Veronica Ortiz 05/01/2015 09:44 AM
Auditor's Office Monica Salinas 05/01/2015 03:24 PM
Form Started By:
moysalazar
Started On:
04/30/2015 02:43 PM
Final Approval Date:
05/01/2015