AI - 51760
14.
DRAINAGE DISTRICT
- Meeting Date:
- 10/13/2015
- Submitted By:
- Claudette Guerrero, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Request approval to issue payment on the following items:
A. Application for Payment No. 2 in the amount of $105, 225.18 from GO Excavating related to Construction Contract No. HCDD1-14-031-12-02 Spanish Palms Subdivision. Project Engineer: Tedsi Infrastructure Group.
B. Application for Payment No. 3-Retainage Release in the amount of $30,203.77 from GO Excavating related to Construction Contract No. HCDD1-14-031-12-02 Spanish Palms Subdivision. Project Engineer: Tedsi Infrastructure Group.
C. Approval of Certificate of Substantial Completion from GO Excavating for Construction Project No. HCDD1-14-031-12-02 Spanish Palms Subdivision. Project Engineer: Tedsi Infrastructure Group.
D. Approval of Certificate of Completion from GO Excavating for Construction Contract No. HCDD1-14-031-12-02 Spanish Palms Subdivision. Project Engineer: Tedsi Infrastructure Group.
A. Application for Payment No. 2 in the amount of $105, 225.18 from GO Excavating related to Construction Contract No. HCDD1-14-031-12-02 Spanish Palms Subdivision. Project Engineer: Tedsi Infrastructure Group.
B. Application for Payment No. 3-Retainage Release in the amount of $30,203.77 from GO Excavating related to Construction Contract No. HCDD1-14-031-12-02 Spanish Palms Subdivision. Project Engineer: Tedsi Infrastructure Group.
C. Approval of Certificate of Substantial Completion from GO Excavating for Construction Project No. HCDD1-14-031-12-02 Spanish Palms Subdivision. Project Engineer: Tedsi Infrastructure Group.
D. Approval of Certificate of Completion from GO Excavating for Construction Contract No. HCDD1-14-031-12-02 Spanish Palms Subdivision. Project Engineer: Tedsi Infrastructure Group.
BACKGROUND
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 10/09/2015 11:31 AM |
- Form Started By:
- ccavazos
- Started On:
- 10/09/2015 11:18 AM
- Final Approval Date:
- 10/09/2015