AI- 51778
Purchasing Department 8.B.
CC CONSENT
- Meeting Date:
- 10/21/2015
- Submitted For:
- Marcie Jackson
- Submitted By:
- Moises Salazar, PURCHASING DEPT.
- Department:
- COMM. PCT. #1
Information
CAPTION
Ratification of fully executed Change Order No. 6 in connection to contract No. C-14-362-10-28 with 2GS, LLC for the project: -Hidalgo County Precinct #1 -SIOUX ROAD PAVING & DRAINAGE IMPROVEMENTS PROJECT [from Tower Road to Val Verde Road] as recommended by Mr. Raul Sesin, P.E.
BACKGROUND
Additional 60 calendar days for project completion.
Fiscal Impact
- FISCAL YEAR:
- 2015
- ACCT. #:
- 5-1XXX-431-00-121-183-0-721
- FUNDS AVAILABLE Y/N?:
- YES
- MATCHING FUNDS Y/N?:
- NO
BUDGETARY IMPACT:
Additional costs to project = $0.05Time extension = 11
PO# 717811
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 10/15/2015 03:50 PM |
| Budget and Management | Veronica Ortiz | 10/15/2015 04:01 PM |
| Auditor's Office | Monica Salinas | 10/16/2015 04:53 PM |
- Form Started By:
- moysalazar
- Started On:
- 10/14/2015 08:27 AM
- Final Approval Date:
- 10/16/2015