AI- 53838
Urban County 16.F.
CC - REGULAR
- Meeting Date:
- 03/22/2016
- Submitted For:
- Diana Serna
- Submitted By:
- Sandra Regalado, URBAN COUNTY
- Department:
- URBAN COUNTY
Information
CAPTION
1. Urban County Program is requesting approval of Change Order No. 3 to a construction contract with Saenz Brothers Construction, LLC for a City of La Villa - Waste Water Improvements Project. The Change Order will increase the construction contract amount by $116,231.70 for a total construction contract amount of $699,231.70 utilizing FY 26 (2013) La Villa Water/Sewer Improvements funds.
2. Consideration and approval to authorize the UCP Director to sign this Change Order.
2. Consideration and approval to authorize the UCP Director to sign this Change Order.
BACKGROUND
The Change Order request is due to construction of all-weather road access to existing mechanical building and construction of a new headworks facility and the replacement of existing weir gate at oxidation ditch outfall.
Contractor: Saenz Brothers Construction LLC
Contract Amount: $583,000.00
Change Order No.1: $116,231.70
New Contract Amount: $699,231.70
Funds Available: $121,579.41 FY 27 (2013) Water/Sewer Improvements
Contractor: Saenz Brothers Construction LLC
Contract Amount: $583,000.00
Change Order No.1: $116,231.70
New Contract Amount: $699,231.70
Funds Available: $121,579.41 FY 27 (2013) Water/Sewer Improvements
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 03/18/2016 08:10 AM |
| Final Approval | Monica Salinas | 03/18/2016 04:47 PM |
- Form Started By:
- sregalado
- Started On:
- 03/17/2016 02:05 PM
- Final Approval Date:
- 03/18/2016