AI - 62950
5.
DRAINAGE - CONSENT
Meeting Date:
12/19/2017
Submitted For:
Jaime Salazar
Submitted By:
Moises Salazar, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the fully executed Change Order No. 2, reflecting an increase of $13,500.00 to contract amount, and 292 additional calendar days, in connection with contract No. C-HCDD1-16-040-08-16 -Hidalgo County Drainage District No. 1 "Drainage Improvements Project East Donna Drain -Flood Pump" with MOR-WIL, LLC, as recommended by project engineer TEDSI Infrastructure Group, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM, subject to compliance with HB1295 when and if applicable.

BACKGROUND