AI - 67042
3.
DRAINAGE - CONSENT
- Meeting Date:
- 10/09/2018
- Submitted For:
- Raul Sesin
- Submitted By:
- Lora Briones, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Approval of Engineering invoices funded by the General Fund:
| Invoice# | Engineering Firm | Amount | WA # | PO# | Project |
| 50029 | B2Z | $20,915.21 | 3 | 634059 | Study Precinct #1 |
| 50034 | B2Z | $ 6,288.42 | 1 | 632784-18 | Administration |
| 50037 | B2Z | $37,500.74 | 3 | 634059 | Study Precinct #1 |
| 50032 | B2Z | $10,307.28 | 1 | 632205 | Study Precinct #2 & #4 |
| 18-8-000014 | L&G | $ 913.58 | 1 | 633601 | Alamo Lateral-C C Phase II CMT |
| 11327134 | L&G | $ 8,424.96 | 1 | 634023 | ROW Acq, PS&E Weslaco N Lateral Ditch |
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 10/05/2018 05:16 PM |
- Form Started By:
- Lora Briones
- Started On:
- 10/04/2018 03:09 PM
- Final Approval Date:
- 10/05/2018