CAPTION
Requesting approval of Change Order No. 2 reflecting an increase in the amount of $84,351.51 and seven (7) additional calendar days, in connection with contract No. C-HCDD1-18-002-05-22 -Hidalgo County Drainage District No. 1 "New Administration Building" with Bullard Construction, Inc., as recommended by project engineer Halff Associates, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM, subject to compliance with HB1295 when and if applicable.