2.
DRAINAGE - CONSENT
Meeting Date:
01/09/2019
Submitted For:
Jaime Salazar
Submitted By:
Moises Salazar, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the fully executed Change Order No.3 reflecting an increase of ninety four (94) construction calendar days, in connection with contract No. C-HCDD1-18-020-05-08 -Hidalgo County Drainage District No. 1 "HCDD1 J-09 Drain Improvements Phase III -Roadway & Field Crossings" with Castle Enterprises, LLC, as recommended by project engineer TEDSI Infrastructure Group, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM. (subject to compliance to HB1295)

BACKGROUND

Form HB1295 has been submitted.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 01/04/2019 06:25 PM
Form Started By:
moysalazar
Started On:
12/28/2018 04:18 PM
Final Approval Date:
01/04/2019