CAPTION
Approval to issue payment on the following item(s) proceeding review & compliance of contract terms & conditions:
CIP 133-2013 Bonds
Bdgt: 370- Pct1 Donna North Lateral Control Structure
Bdgt: 370-Pct2 FM 495 Drain Control Structure
Application for Payment No. 1 in the amount of $131,813.91 from Venser Contractors, LLC pertaining to Construction Contract No. HCDD1-18-049-09-19 FM 495 Drain Control Structure & Donna North Lateral Control Structure.
PO#636130 - Project Engineer: Jose N. Saldivar, P.E.-Hidalgo County Drainage District No. 1
CIP 133-2013 Bonds
Bdgt: 370- Pct1 Donna North Lateral Control Structure
Bdgt: 370-Pct2 FM 495 Drain Control Structure
Application for Payment No. 1 in the amount of $131,813.91 from Venser Contractors, LLC pertaining to Construction Contract No. HCDD1-18-049-09-19 FM 495 Drain Control Structure & Donna North Lateral Control Structure.
PO#636130 - Project Engineer: Jose N. Saldivar, P.E.-Hidalgo County Drainage District No. 1
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 01/25/2019 05:46 PM |
- Form Started By:
- ccavazos
- Started On:
- 01/25/2019 11:48 AM
- Final Approval Date:
- 01/25/2019