AI- 7041
18.H.1.
CC REGULAR
Meeting Date:
12/18/2007
Submitted By:
Laura Moya, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Presentation for consideration, discussion acceptance and approval of Change Order No 1 for  LAS HACINEDAS Subdivision  C-CAP-07-023-08-07 adding 15 days to the original contract time with no fiscal impact project engineer is R. Gutierrez Engineering Corporation, and contractor is TRC Utilities, a Border Colonia Access Program Project(s).

BACKGROUND


Fiscal Impact

FISCAL YEAR:
ACCT. #:
7-1311-431-00-122-412-0-733/841
FUNDS AVAILABLE Y/N?:
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

NO BUDGET IMPACT

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 12/12/2007 01:01 PM
Budget and Management Dina Trevino 12/12/2007 02:03 PM
Rey Salazar Rey Salazar 12/13/2007 02:29 PM
Auditor's Office aduran 12/14/2007 05:23 PM
Court Administrator Monica Salinas 12/14/2007 05:32 PM
Form Started By:
lmoya
Started On:
12/12/2007 11:12 AM
Final Approval Date:
12/14/2007