AI- 7044
18.C.2.
CC REGULAR
- Meeting Date:
- 12/18/2007
- Submitted For:
- Rocio Villarreal
- Submitted By:
- Rocio Villarreal, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Requesting approval of Change Order No. 3 (increasing of contract time only) in connection with "Installation of 36-inch RCP and Misc. Items" from McAllen Construction, as recommended by project engineer R. Gutierrez Engineering Corporation, and with authority for County Judge to execute document with no impact on total contract amount;
BACKGROUND
C-06-368-10-31
Fiscal Impact
- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1202-431-00-122-006-0-841
- FUNDS AVAILABLE Y/N?:
- y
- MATCHING FUNDS Y/N?:
- n
BUDGETARY IMPACT:
NO BUDGETARY IMPACT. Purchase Order No. 581509Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 12/12/2007 01:01 PM |
| Budget and Management | Dina Trevino | 12/12/2007 02:05 PM |
| Rey Salazar | Rey Salazar | 12/13/2007 09:48 AM |
| Auditor's Office | jhsu | 12/14/2007 03:09 PM |
| Court Administrator | Monica Salinas | 12/14/2007 03:21 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 12/12/2007 11:22 AM
- Final Approval Date:
- 12/14/2007