CAPTION
Approval to issue payment on the following items proceeding review & compliance of contract terms & conditions: J09 Drainage Improvements-Budget 300
1.Acceptance of Certificate of Substantial Completion from Castle Enterprises, LLC pertaining Construction Contract No. HCDD1-18-020-05-08 J09 Drainage Improvements Phase III. Project Engineer: Jose Noe Saldivar, P.E.-HCDD1
2.Application for payment No. 11 in the amount of $34,739.20 from Castle Enterprises, LLC pertaining Construction Contract No.HCDD1-18-020-05-08 J09 Drainage Improvements Phase III. Project Engineer: Jose N. Saldivar, P.E.-HCDD1 PO#634761
Approval to issue payment on the following items proceeding review & compliance of contract terms & conditions: Iowa Rd Drainage Improvements-Budget 365-040-013
3. Application for payment no. 1 in the amount of $161,909.24 from Castle Enterprises, LLC pertaining Construction Contract No. HCDD1-18-048-09-25 Iowa Rd Drainage Improvements. Project Engineer: Jose Noe Saldivar, P.E.-HCDD1 PO#637966
4. Application for payment no. 2 in the amount of $84,967.19 from Castle Enterprises, LLC pertaining Construction Contract No. HCDD1-18-048-09-25 Iowa Rd Drainage Improvements. Project Engineer: Jose Noe Saldivar, P.E. -HCDD1 PO#637966
1.Acceptance of Certificate of Substantial Completion from Castle Enterprises, LLC pertaining Construction Contract No. HCDD1-18-020-05-08 J09 Drainage Improvements Phase III. Project Engineer: Jose Noe Saldivar, P.E.-HCDD1
2.Application for payment No. 11 in the amount of $34,739.20 from Castle Enterprises, LLC pertaining Construction Contract No.HCDD1-18-020-05-08 J09 Drainage Improvements Phase III. Project Engineer: Jose N. Saldivar, P.E.-HCDD1 PO#634761
Approval to issue payment on the following items proceeding review & compliance of contract terms & conditions: Iowa Rd Drainage Improvements-Budget 365-040-013
3. Application for payment no. 1 in the amount of $161,909.24 from Castle Enterprises, LLC pertaining Construction Contract No. HCDD1-18-048-09-25 Iowa Rd Drainage Improvements. Project Engineer: Jose Noe Saldivar, P.E.-HCDD1 PO#637966
4. Application for payment no. 2 in the amount of $84,967.19 from Castle Enterprises, LLC pertaining Construction Contract No. HCDD1-18-048-09-25 Iowa Rd Drainage Improvements. Project Engineer: Jose Noe Saldivar, P.E. -HCDD1 PO#637966
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 12/06/2019 03:31 PM |
- Form Started By:
- ccavazos
- Started On:
- 12/05/2019 03:43 PM
- Final Approval Date:
- 12/06/2019