AI- 74595
Purchasing Department   13.A.
CC CONSENT AGENDA SPECIAL MTG
Prct. 2
Meeting Date:
02/26/2020
Submitted For:
Eddie Cantu
Submitted By:
Erika Zamora, COMM. PCT. #2
Department:
COMM. PCT. #2

CAPTION

Requesting approval of Change Order Nos. 1 through 3 (C-19-017-11-15) with 2GS, LLC dba Earthworks Enterprise for the Hidalgo County Precinct #2 - Dicker Road Reconstruction Project from (23rd Street to Jackson Road) as recommended by the project engineer, Saul Muñoz, P.E.

BACKGROUND

CO #1-Modify Traffic Control Plan from 23rd to 10th St and reduce construction cost;
CO #2-additional culverts needed due to plan error;
CO #3-waterline construction work added through ICA between County and Mcallen PUB

Change Orders 1 through 3 will increase the contract $287,083.94.

Fiscal Impact

CALENDAR YEAR:
2020
ACCT. #:
0-1315-431-00-122-062-0-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding for Change Order No. 1 and 2 will be covered within the current PO.
Funding for Change Order No. 3 will be provided by Mcallen PUB within 30 days of executing the change order as provided in the interlocal agreement approved by CC 6/6/19 AI#70659.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 02/21/2020 05:50 PM
Final Approval Monica Salinas 02/21/2020 05:56 PM
Form Started By:
Erika Zamora
Started On:
02/21/2020 04:26 PM
Final Approval Date:
02/21/2020