CAPTION
Approval of Application for Payment No. 6 in the amount of $268,877.49 to Erickson Construction, LLC. for the "Construction Manager at Risk (CMAR) for the Pct 2 Las Milpas Park Youth Facility Project GMP Amendment #2", through Contract# C-17-324-07-17, and as certified for payment by the project engineer, B2Z Engineering, LLC.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2020
- ACCT. #:
- 0-1XXX-451-22-122-141-X-730
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding available through PO #795831 for Erickson Construction, LLC, in the amount of $1,132,160.24 as of 08/07/20.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | broque | 08/07/2020 07:19 PM |
| Final Approval | Monica Salinas | 08/07/2020 08:40 PM |
- Form Started By:
- Lupita Garza
- Started On:
- 08/07/2020 01:58 PM
- Final Approval Date:
- 08/07/2020