Approval to issue payment on the following item proceeding review & compliance of contract terms and conditions:
Mission Lateral Budget 526
1. Application for Payment No.3 in the amount of $408,127.50-Saenz Brothers Construction, LLC pertaining to Construction Contract No. HCDD1--19-074-11-26 Project Engineer: L&G Consulting Engineering PO#639234-R
Mission Lateral Budget 526
1. Application for Payment No.3 in the amount of $408,127.50-Saenz Brothers Construction, LLC pertaining to Construction Contract No. HCDD1--19-074-11-26 Project Engineer: L&G Consulting Engineering PO#639234-R
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 11/06/2020 05:15 PM |
- Form Started By:
- ccavazos
- Started On:
- 11/06/2020 10:21 AM
- Final Approval Date:
- 11/06/2020