AI - 79402
4.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 02/02/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 1 reflecting Sixty (60) additional construction calendar days, in connection with Contract No. C-HCDD1-20-026-06-23 -Hidalgo County Drainage District No. 1 "PD Lateral (Phase 1) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, LLC, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.
BACKGROUND
HB1295 Form has been submitted.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 01/29/2021 04:52 PM |
- Form Started By:
- moysalazar
- Started On:
- 01/29/2021 11:26 AM
- Final Approval Date:
- 01/29/2021