CAPTION
Requesting ratification of approved Notice to Suspend Work Order No. 2, issued to Mor-Wil, LLC, awarded contractor for Contract No. C-HCDD1-20-001-02-11, "Hidalgo Drain & Dicker Road Box Culvert Crossing" as approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM., with Suspend Work Order No. 2 Effective Date of: January 22, 2021.
BACKGROUND
Suspend Work Order No. 2 issued to allow time for field and contract issues by other entities involved be resolved.
Fiscal Impact