AI- 80156
Purchasing Department 18.E.3.
CC REGULAR AGENDA REGULAR MTG
Prct. 4
- Meeting Date:
- 03/30/2021
- Submitted For:
- Nick Perez
- Submitted By:
- Nick Perez, COMM. PCT. #4
- Department:
- COMM. PCT. #4
CAPTION
A. Requesting acceptance and approval of the Certificate of Substantial Completion, reflecting the date of January 29, 2021, submitted by RG Enterprises, LLC d/b/a G&G Contractors, awarded contractor for the Precinct 4 -Storage Facility Mezzanine Project, and as certified by the project engineer, Halff Associates, Inc. under "on call" agreement, C-19-252-07-16 (WA#3);
B. Requesting acceptance and approval of Payment Application No. 3 (Final) in the amount of $11,954.70 for RG Enterprises, LLC d/b/a G&G Contractors for the Hidalgo County Precinct 4 Storage Addition as submitted by project engineer, Halff Associates, Inc.
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
FUNDS AVAILABLE UNDER P.O. 821144Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/25/2021 03:50 PM |
| Budget and Management | Veronica Ortiz | 03/26/2021 08:28 AM |
| Final Approval | Monica Salinas | 03/26/2021 06:54 PM |
- Form Started By:
- Nick Perez
- Started On:
- 03/25/2021 01:15 PM
- Final Approval Date:
- 03/26/2021