AI - 80370
3.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 04/13/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Rocio Villarreal, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 1 reflecting eighty-seven (87) additional construction calendar days, in connection with Contract C-HCDD1-20-044-09-15-"Old La Blanca Rd & Mile 10 N-2018 Bond Referendum-Project #28" with Venser Contractors, LLC, and as recommended by Project Engineer, Guzman & Munoz Engineering & Surveying, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM. (subject to compliance to HB1295)
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 04/09/2021 05:26 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 04/09/2021 02:27 PM
- Final Approval Date:
- 04/09/2021