AI - 80939
6.B.
DD-REGULAR AGENDA REGULAR MTG
- Meeting Date:
- 05/25/2021
- Submitted By:
- Alvaro Chuc, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
CAPTION
Mile 9 N. & FM 1015 - Budget 524
1. Approval of Application for Payment No. 1 in the amount of $62,505.00 from Mor-Wil, LLC pertaining to Construction Contract No. HCDD1-20-065-11-18. Project Engineer: Halff & Associates, Inc. PO#641649
1. Approval of Application for Payment No. 1 in the amount of $62,505.00 from Mor-Wil, LLC pertaining to Construction Contract No. HCDD1-20-065-11-18. Project Engineer: Halff & Associates, Inc. PO#641649
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 05/21/2021 04:57 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 05/20/2021 09:25 AM
- Final Approval Date:
- 05/21/2021