CAPTION
A. Presentation of scoring grid (for purpose of ranking/qualifying by CC) of the eight (8) responses received, evaluated, and graded by the appointed/designated committee via AI-80123 (3/30/21), for the "Construction of New Justice Center - PCT 4":
| Respondent | ECON | Holechemont, LTD | Morganti | NM Contracting, LLC | SAMES | Summit Building & Design | Terra Fuerte Construction, LLC | Tri-Gen Construction, LLC |
| Evaluator 1 | 93 | 84 | 82 | 86 | 85 | 83 | 72 | 87 |
| Evaluator 2 | 90 | 96 | 78 | 99 | 81 | 85 | 70 | 88 |
| Evaluator 3 | 97 | 95 | 96 | 93 | 90 | 92 | 98 | 91 |
| Evaluator 4 | 93 | 93 | 90 | 94 | 91 | 92 | 86 | 90 |
| Evaluator 5 | 98 | 91 | 97 | 89 | 84 | 87 | 66 | 86 |
| Totals | 471 | 459 | 443 | 461 | 431 | 439 | 392 | 442 |
| Rank |
B. Authority for the Purchasing Department to commence negotiations with number 1 ranked firm of __________________ for the Construction of a New Justice Center located in PCT 4.
BACKGROUND
Reference AI-80123 (3/30/21) for designated/appointed evaluation committee
Project No: 21-229-JDC
Project No: 21-229-JDC
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Fiscal impact is through CIP proceeds.Attachments
- CC MoM - Evaluator Appointments - New Justice Center
- No Conflict Disclosure Forms
- Justice Center Evaluation Results-Scoring Grid Revised
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 07/09/2021 04:17 PM |
| Budget and Management | Veronica Ortiz | 07/09/2021 04:19 PM |
| Final Approval | Monica Salinas | 07/10/2021 09:16 AM |
- Form Started By:
- jcortez
- Started On:
- 07/06/2021 04:29 PM
- Final Approval Date:
- 07/10/2021