CAPTION
1. Ratification of the fully executed Change Order No. 3 reflecting fifty-seven (57) additional construction calendar days, in connection with Contract No. C-HCDD1-20-026-06-23 - "PD Lateral (Phase 1) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, LLC, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.
2. Ratification of the fully executed Change Order No. 4 reflecting an additional amount of $45,363.52, and twenty (20) additional construction calendar days, in connection with Contract No. C-HCDD1-20-026-06-23 -"PD Lateral (Phase 1) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, LLC, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.
2. Ratification of the fully executed Change Order No. 4 reflecting an additional amount of $45,363.52, and twenty (20) additional construction calendar days, in connection with Contract No. C-HCDD1-20-026-06-23 -"PD Lateral (Phase 1) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, LLC, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 10/29/2021 05:26 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 10/18/2021 03:30 PM
- Final Approval Date:
- 10/29/2021