CAPTION

1.  Ratification of the fully executed Change Order No. 3 reflecting fifty-seven (57) additional construction calendar days, in connection with Contract No. C-HCDD1-20-026-06-23 - "PD Lateral (Phase 1) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, LLC, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.

2.  Ratification of the fully executed Change Order No. 4 reflecting an additional amount of $45,363.52, and twenty (20) additional construction calendar days, in connection with Contract No. C-HCDD1-20-026-06-23 -"PD Lateral (Phase 1) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, LLC, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 10/29/2021 05:26 PM
Form Started By:
Rocio Villarreal
Started On:
10/18/2021 03:30 PM
Final Approval Date:
10/29/2021