AI - 83344
4.C.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 11/16/2021
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 4 reflecting sixty (60) additional calendar days, in connection with Construction Contract C-HCDD1-20-041-09-15-"Sunflower Drain -2018 Bond Referendum Project #36" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Jaime Salazar | 11/12/2021 04:23 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/10/2021 08:15 AM
- Final Approval Date:
- 11/12/2021