Acceptance and approval of Supplemental Agreement No. 1 for services under Work Authorization No. 4, through Contract No. C-HCDD1-20-027-05-19 with B2Z Engineering, LLC, resulting in an estimated cost increase of $73,419.86, for Additional Services for the P.S.J.A. Lateral Drain Ditch improvements (subject to Legal Review).