AI - 84549
7.A.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 02/08/2022
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 3 an increase in the amount of $253,113.50, and additional One hundred and twenty (120)calendar days, in connection with the construction Contract C-HCDD1-20-063-11-12, “P.S.J.A. Lateral Drain Ditch Improvements (Earling Road to South Main Drain Phase I)" with Saenz Brothers Construction, LLC, and as recommended by Project Engineer, Javier Hinojosa Engineering (subject to compliance to HB1295).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 02/04/2022 05:31 PM |
- Form Started By:
- moysalazar
- Started On:
- 02/04/2022 04:07 PM
- Final Approval Date:
- 02/04/2022