Information

CAPTION

Requesting approval of Change Order No. 7 reflecting an increase in the amount of $60,109.36, and Ninety (90) additional construction calendar days, in connection with Contract No. C-HCDD1-20-002-02-11 -"Mission
Inlet Drainage Improvements Project (Section C & F-Balboa Estates Area Drainage Improvements)'' with Castle Enterprises, LLC, as recommended by Project Engineer, L&G Engineering.

BACKGROUND

Description:
-Contract Time Extension (90 days)
-Additional Excavation Quantities $60,109.36

Reason for Change Order:
-Delays due to property owner conflicts
-Weather delays
-Additional volume added to Mission Inlet Drain System

Compliance with HB 1295
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 05/27/2022 05:13 PM
Form Started By:
Enriqueta Zambrano
Started On:
05/17/2022 11:42 AM
Final Approval Date:
05/27/2022