AI - 86903
5.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 08/09/2022
- Submitted For:
- Jaime Salazar
- Submitted By:
- Enriqueta Zambrano, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 8 reflecting twenty (20) additional calendar days, in connection with Construction Contract C-HCDD1-20-041-09-15-"Sunflower Drain -2018 Bond Referendum Project #36" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Project completion date with this CO8
August 24, 2022
August 24, 2022
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 08/05/2022 05:46 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 08/04/2022 04:52 PM
- Final Approval Date:
- 08/05/2022