CAPTION
Requesting approval of Change Order No. 7 with Saenz Brothers Construction (C-HCDD1-21-027-07-27) to reflect an increase amount of $65,500.00 with an additional thirty (30) Days for the project of, "Mission Lateral Phase III(Proposed Widening of Ditch from Bentsen Palm Drive to the West of Wagon City 2 Subdivision)-2018 Bond Referendum Project #26," and as recommended by project engineer, L&G Engineering. (subject to HB 1295 compliance)