CAPTION
Ratification of the approved and fully executed Change Order No. 8 with RG Enterprises, LLC dba G & G Contractors (C-HCDD1-20-034-08-11) reflecting an increase of ninety (90) calendar days to the Jackson Road Drain – 2018 Bond Referendum Project 16 Project as recommended by Project Engineer, Quintanilla, Headley & Associates and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.