CAPTION
Main Floodwater Channel Weir 4- Budget 375
Approval of Application for Payment No. 1 in the amount of $38,166.71 from Clore Equipment, LLC pertaining to Construction Contract C-HCDD1-22-030-07-12 MFW Channel Weir 4. Project Engineer: International Consulting Engineers, PO#646926
Approval of Application for Payment No. 1 in the amount of $38,166.71 from Clore Equipment, LLC pertaining to Construction Contract C-HCDD1-22-030-07-12 MFW Channel Weir 4. Project Engineer: International Consulting Engineers, PO#646926
BACKGROUND
Fiscal Impact