CAPTION

East Mercedes - Budget 510
1. Approval of Application for Payment No. 2 in the amount of $320,167.89 from RBM Contractors pertaining to Construction Contract C-HCDD1-22-051-01-17 East Mercedes. Project Engineer: HCDD1 Yvette Barrera, PE, CFM PO#647299

Mission McAllen Rado Phase I - Budget 525
2. Approval of Application for Payment No. 9 in the amount of $112,606.02 from Gonzalez Engineering pertaining to Construction Contract C-HCDD1-21-023-07-27 Mission McAllen Rado Phase I. Project Engineer: B2Z Engineering PO#642887

Mission McAllen Rado Phase II - Budget 525
3. Approval of Application for Payment No. 3 in the amount of $17,374.50 from Texas Cordia Construction, LLC pertaining to Construction Contract C-HCDD1-22-003-02-22 Mission McAllen Rado Phase II. Project Engineer B2Z Engineering PO#645638

4. Approval of Application for Payment No. 4 in the amount of $56,801.45 from Texas Cordia Construction, LLC pertaining to Construction Contract C-HCDD1-22-003-02-22 Mission McAllen Rado Phase II. Project Engineer B2Z Engineering PO#645638

Mission Lateral Budget - 526
5. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Saenz Brothers Construction, LLC pertaining to Construction Contract C-HCDD1-21-027-07-27 Mission Lateral Phase III.  Project Engineer: L&G Engineering

6. Approval of Application for Payment No. Retainage & Interest in the amount $267,563.44 from Saenz Brothers Construction pertaining to construction contract C-HCDD1-21-027-07-27

South I Rd Detention (West Side) - Budget 533
7. Approval of Application for Payment No. 5 in the amount of $74,875.75 from IOC Company pertaining to Construction Contract C-HCDD1-22-028-07-12 South I Rd Detention (West Side). Project Engineer: B2Z Engineer PO#646281
 
South Lateral Drain Structure - Budget 534 
8. Approval of Application for Payment No. 1 in the amount of $75,570.30 from Mor-Wil, LLC pertaining to Construction Contract C-HCDD1-22-033-07-12 South Lateral Drain Structure. Project Engineer: HCDD1 Yvette Barrera, PE, CFM PO#646381

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 05/12/2023 04:18 PM
Form Started By:
Alvaro Chuc
Started On:
05/12/2023 08:33 AM
Final Approval Date:
05/12/2023