CAPTION
Ratification of approved and fully executed Change Order No. 1, reflecting twenty (20) additional days, and an increase of $29,400, in connection with the project "Mile 10 N & Baseline Rd. -2018 Bond Referendum Project No. 20’', Contract (C-HCDD1-22-065-03-07), with H2O Construction Services, Inc., as recommended by Project Engineer, Quintanilla Headley and Associates (QHA).
BACKGROUND
Project completion date as per CO1: January 07, 2024