CAPTION

Ratification of the approved and fully executed Change Order No.2, reflecting a decrease in the amount of ($12,845.96) and 120 additional construction calendar days, for "Mid-Valley Airport Ditch 18B Drainage Improvements - 2018 Bond Referendum Project No. 19’', Contract No. C-HCDD1-22-020-05-31, with Mor-Wil, LLC, as recommended by Project Manager, B2Z Engineering, LLC.and approved by HCDD1 District General Manager, Raul E. Sesin, P.E., CFM.

BACKGROUND

Project completion date: December 21, 2023