AI - 93365
5.E.
DD-REGULAR AGENDA REGULAR MTG
- Meeting Date:
- 11/28/2023
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
CAPTION
Requesting approval of Change Order No. 1 for an increase in the amount of $108,912.10 and Sixty (60) additional construction calendar days, in connection with the project "Drainage Area Improvements for Y Drain Ph I, Tower Rd between Rogers & Monte Cristo & Curry Drain & Valverde Rd Crossings,'', Contract No. C-HCDD1-21-050-R-05-30, with Mor-Wil, LLC, as recommended by Project Engineer, Asst. District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 11/22/2023 05:01 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 11/21/2023 03:28 PM
- Final Approval Date:
- 11/22/2023