CAPTION
North Main Drain Edinburg - Budget 204
1. Approval of Application for Payment No. 4 in the amount of $302,895.22 from Welch Excavation pertaining to Construction Contract No. C-HCDD1-22-066-05-02. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#647845
1. Approval of Application for Payment No. 4 in the amount of $302,895.22 from Welch Excavation pertaining to Construction Contract No. C-HCDD1-22-066-05-02. Project Engineer HCDD1 Omar Anzaldua, Jr., PE, CFM PO#647845
BACKGROUND
Fiscal Impact
Attachments