CAPTION
A. Requesting approval of "Certificate of Completion" with Asago Construction, LLC, reflecting the completion date of May 8, 2008 for the "Construction of Tamarron Estates-Drainage Improvments" for Hidalgo County Precinct No. 4 and as certified by project engineer, Quintanilla, Headley & Associates, Inc. in connection to Contract No. C-07-355-10-23.
B. Presentation for consideration, discussion acceptance and approval of Work Authorization No. 7 in the amount of $ 2,116.31 with MILLENNIUM ENGINEERS GROUP, INC. to provide engineering services to Hidalgo County Precinct No. 4 in connection with Contract No. C-07-265-10-15 for the "Construction Materials Testing Services for PAVED/UN-PAVED, LATERAL and CIP PROJECTS (North Doolittle Road (North of FM 2812)"
BACKGROUND
Work Authorization No. 7-Millenium Engineers Group, Inc.
Fiscal Impact
- FISCAL YEAR:
- 2008
- ACCT. #:
- 8-1204-431-00-124-007-0-733
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO# 594450 has available $35,750.00 as of 5/22/08. Funds available as of 5/22/08. Payment#4 (Final) and Payment#5 (Retainage) were requested 5-19-08 CC AI#9318.- FISCAL YEAR:
- 2008
- ACCT. #:
- 8-1204-431-00-124-007-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Account available balance as of 5/22/08 $269,681.42.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 05/21/2008 01:02 PM |
| Budget and Management | Dina Trevino | 05/21/2008 01:30 PM |
| Auditor's Office | lfong | 05/22/2008 12:09 PM |
| Court Administrator | Alejandro Garcia | 05/23/2008 10:00 AM |
- Form Started By:
- Letty Saenz
- Started On:
- 05/21/2008 11:20 AM
- Final Approval Date:
- 05/23/2008