AI - 94774
2.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 04/02/2024
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No.4, reflecting an increase in the amount of $7,557.81 for the project "Drainage Area Improvements for Y Drain Ph I, Tower Rd Between Rogers & Monte Cristo & Curry Drain & Valverde Rd Crossings’', (C-HCDD1-21-050-R-05-30), with Mor-Wil, LLC, as recommended by Project Engineer, Asst. District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM and approved by HCDD1 General Manager, Raul Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/28/2024 03:10 PM |
- Form Started By:
- Justin Silva
- Started On:
- 03/28/2024 09:18 AM
- Final Approval Date:
- 03/28/2024