CAPTION
South Main Drain Phase 2 - Budget 703
Approval of Application for Payment No. 3 in the amount of $633,521.39 from E-Con Group pertaining to construction contract C-HCDD1-24-007-03-19 South Main Drain Phase 2. Project Engineer HCDD1 Omar Anzaldua, Jr. PE. CFM PO#649085
Approval of Application for Payment No. 3 in the amount of $633,521.39 from E-Con Group pertaining to construction contract C-HCDD1-24-007-03-19 South Main Drain Phase 2. Project Engineer HCDD1 Omar Anzaldua, Jr. PE. CFM PO#649085
BACKGROUND
Fiscal Impact