CAPTION
M10 N & Baseline - Budget 520
1. Approval of Application for Payment No. 12 in the amount of $44,461.71 from RBM Contractors pertaining to construction contract HCDD1-23-014-04-26KMG Mile 10 N & Baseline. Project Engineer Quintanilla Headley PO#648064
Glasscock Rd (Mile 4 to Mile 5) - Budget 543
2. Approval of Application for Payment No. 6 in the amount of $223,816.20 from Saenz Brothers Construction pertaining to construction contract HCDD1-23-051-09-27ESZ. Project Engineer J&R Engineering PO#648791
1. Approval of Application for Payment No. 12 in the amount of $44,461.71 from RBM Contractors pertaining to construction contract HCDD1-23-014-04-26KMG Mile 10 N & Baseline. Project Engineer Quintanilla Headley PO#648064
Glasscock Rd (Mile 4 to Mile 5) - Budget 543
2. Approval of Application for Payment No. 6 in the amount of $223,816.20 from Saenz Brothers Construction pertaining to construction contract HCDD1-23-051-09-27ESZ. Project Engineer J&R Engineering PO#648791
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/27/2024 04:20 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 09/27/2024 01:47 PM
- Final Approval Date:
- 09/27/2024