CAPTION
Pharr McAllen Lateral East - Budget 709
Approval of Application for Payment No. 1 in the amount of $179,578.80 from Synergy Development & Construction pertaining to construction contract HCDD1-24-029-06-11 Pharr Mcallen Lateral. Project Engineer GDJ Engineering PO#649635
Approval of Application for Payment No. 1 in the amount of $179,578.80 from Synergy Development & Construction pertaining to construction contract HCDD1-24-029-06-11 Pharr Mcallen Lateral. Project Engineer GDJ Engineering PO#649635
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 09/27/2024 04:20 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 09/27/2024 01:51 PM
- Final Approval Date:
- 09/27/2024