Information

CAPTION

Requesting approval of Change Order No. 1 (Increase) in the amount of $7,674.00 in connection with the "South Tower Park Project" from contracted vendor, Sanchez United Contracting, Inc., and as recommended by project engineer, R. Gutierrez Engineering Corp., with authority for County Judge or Court member to execute document.

BACKGROUND

Original Contract Price of $223,399.50 is being funded by Urban County. (Project RFB #5007-92-0306-5000-9200-ML located in Pct. #2)

Fiscal Impact

FISCAL YEAR:
2008
ACCT. #:
8-1212-452-00-122-008-0-739
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Available balance is $172,178.19 as of 6/13/08.  Precinct 2 Parks funds are available for pending Change Order Number One (increase of $7,674.00) for Urban County project at South Tower Park.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 06/13/2008 12:21 PM
Budget and Management Dina Trevino 06/13/2008 03:03 PM
Form Started By:
Rocio Villarreal
Started On:
06/13/2008 11:08 AM
Final Approval Date:
06/13/2008