CAPTION
Requesting acceptance and approval of Change Order No. 1 from Saenz Brothers Construction, for the "J-01 Stormwater Management Project" (C-24-0337-10-29) to reflect the additional materials and increase the contract price by $6,880.00, with an additional 60 calendar days beyond the original contract completion date, as recommended by the Engineering firm TEDSI Infrastructure Group.
BACKGROUND
Additional items were required as a result of the vandalism at Ramseyer Road.
New Contract Price: $1,325,114.50
New Contract Price: $1,325,114.50
Fiscal Impact
- CALENDAR YEAR:
- 2025
- ACCT. #:
- 5-1200-431-00-124-007-0-723
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funds available as of 5/9/2025.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 05/09/2025 10:34 AM |
| Budget and Management | Veronica Ortiz | 05/09/2025 10:36 AM |
| Final Approval | Monica Salinas | 05/09/2025 05:40 PM |
- Form Started By:
- Cassandra Carr
- Started On:
- 05/07/2025 04:36 PM
- Final Approval Date:
- 05/09/2025