CAPTION

Requesting approval of Change Order No. 3, reflecting an increase in the amount of $831,379.20 and 173 additional construction calendar days for the project “GLO 2015 State MIT Hidalgo County Main Floodwater Channel Expansion Phase 1, Segment B,” Contract No. 22-083-004-D209, with Renoworks, LLC, as recommended by project manager B2Z Engineering and HCDD#1 project engineer Omar Anzaldua.

BACKGROUND

The County of Hidalgo, through its Urban County Program and in partnership with the Texas General Land Office and Hidalgo County Drainage District No. 1, is utilizing funds from the Texas General Land Office State Mitigation Competition Flood Grant to support the Hidalgo County Main Floodwater Channel Expansion, Phase 1, Segment B, spanning from Mile 19 Rd. to Mile 4 Rd. With a contract amount of $9,858,499.20 and an agreement date of November 30, 2021, this project is funded by the U.S. Department of Housing and Urban Development’s Community Development Block Grant - Mitigation Program and aims to restore and enhance drainage infrastructure for communities impacted by the 2015 floods.
 
Contractor Name:                        Renoworks, LLC
Current Contract Amount:                $ 3,962,237.13
Change Order No. 3 Amt:                $ 831,379.20
 Total Contract Amount:                   $ 4,793,616.33
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Veronica Ortiz 05/21/2025 12:20 PM
Final Approval Monica Salinas 05/26/2025 09:34 AM
Form Started By:
Michelle Garza
Started On:
05/21/2025 09:29 AM
Final Approval Date:
05/26/2025