CAPTION

Acceptance and approval of Construction Change Order No. 3 (increase) in the amount of $210.26 and additional (5) days time extension for proposed work with awarded contractor, Saenz Utility Contractors, LTD. ("El Dora Street & Drainage Improvement Project") reflecting items specified on change order description, with authority for County Judge or Court Member to execute document.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1200-431-00-122-052-0-731
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO #662862 available balance of $177,980.05 as of 1/25/2012

New contract amount will be $194,336.81 with 135 calendar days.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 01/26/2012 02:08 PM
Budget and Management mmunoz 01/26/2012 02:16 PM
Auditor's Office Alejandro Garcia 01/31/2012 04:04 PM
Form Started By:
ycisneros
Started On:
01/25/2012 05:28 PM
Final Approval Date:
01/31/2012