AI- 30800
23.C.1.
CC REGULAR
- Meeting Date:
- 02/07/2012
- Submitted For:
- Yoli Cisneros
- Submitted By:
- Yolanda Cisneros, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Acceptance and approval of Construction Change Order No. 3 (increase) in the amount of $210.26 and additional (5) days time extension for proposed work with awarded contractor, Saenz Utility Contractors, LTD. ("El Dora Street & Drainage Improvement Project") reflecting items specified on change order description, with authority for County Judge or Court Member to execute document.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2012
- ACCT. #:
- 2-1200-431-00-122-052-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
PO #662862 available balance of $177,980.05 as of 1/25/2012New contract amount will be $194,336.81 with 135 calendar days.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 01/26/2012 02:08 PM |
| Budget and Management | mmunoz | 01/26/2012 02:16 PM |
| Auditor's Office | Alejandro Garcia | 01/31/2012 04:04 PM |
- Form Started By:
- ycisneros
- Started On:
- 01/25/2012 05:28 PM
- Final Approval Date:
- 01/31/2012