1. North Alamo Water Supply:
a. Vista Bonita Subdivision Phase IV- Bore an 8" PVC waterline with 16" PVC casing, 3,150 feet south of Mile 20 N on the East and West side of Norene Drive.
2. Econ Group, LLC:
a. Hillcrest Terrace Subdivision: Installation of approximately 1,700 LF of 12" PVC sanitary sewer line w/ service connections along Doolittle Drive; 8' from east right-of-way line.
b. Installation of approximately 890 LF of 12" PVC sanitary sewer line w/ service connections along Hillcrest Lane; 11' from west/ 5' from north right-of-way line.
c. Installation of approximately 1,350 LF of 8" PVC sanitary sewer line w/ service connections along Meadow Lane; 5' from east right-of-way line.
a. Vista Bonita Subdivision Phase IV- Bore an 8" PVC waterline with 16" PVC casing, 3,150 feet south of Mile 20 N on the East and West side of Norene Drive.
2. Econ Group, LLC:
a. Hillcrest Terrace Subdivision: Installation of approximately 1,700 LF of 12" PVC sanitary sewer line w/ service connections along Doolittle Drive; 8' from east right-of-way line.
b. Installation of approximately 890 LF of 12" PVC sanitary sewer line w/ service connections along Hillcrest Lane; 11' from west/ 5' from north right-of-way line.
c. Installation of approximately 1,350 LF of 8" PVC sanitary sewer line w/ service connections along Meadow Lane; 5' from east right-of-way line.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Obdett Calzada | 01/09/2013 02:42 PM |
| Auditor's Office | Alejandro Garcia | 01/18/2013 04:59 PM |
- Form Started By:
- Rebecca Gomez
- Started On:
- 01/03/2013 09:40 AM
- Final Approval Date:
- 01/18/2013