AI - 39993
4.
DRAINAGE DISTRICT
- Meeting Date:
- 08/06/2013
- Submitted By:
- Jaime Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
A.) Requesting approval of Change Order No.2 increase of $3,800.00 for Asago, LLC dba Asago Construction as it relates to Edinburg WWTP Effluent Line Roadway Crossings, Project Engineer: Tedsi Infrastructure Group.
B.) Requesting approval to surplus excess bollards left over from the levee projects and approval to transfer to Hidalgo County Pct. 4.
2013 BOND SERIES
C.) Requesting approval to rescind action taken by the HCDD1 Board of Directors on May 28, 2013 as it relates to Pct. 4 San Carlos Regional Project-Dos Logistics, Inc.
B.) Requesting approval to surplus excess bollards left over from the levee projects and approval to transfer to Hidalgo County Pct. 4.
2013 BOND SERIES
C.) Requesting approval to rescind action taken by the HCDD1 Board of Directors on May 28, 2013 as it relates to Pct. 4 San Carlos Regional Project-Dos Logistics, Inc.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Obdett Calzada | 08/02/2013 09:05 AM |
| Final Approval | Monica Salinas | 08/02/2013 04:29 PM |
- Form Started By:
- Jaime Salazar
- Started On:
- 08/01/2013 09:20 AM
- Final Approval Date:
- 08/02/2013