AI- 43615
Purchasing Department 19.C.1.
CC REGULAR
- Meeting Date:
- 03/18/2014
- Submitted For:
- Comm. Tito Palacios, Pct. #2
- Submitted By:
- Erika Zamora, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Requesting approval of Supplemental Agreement No. 1 to Work Authorization No. 1 (an increase in the amount of $11,003.00)for current contract with R. Gutierrez Engineering Corporation for the Pct 2 Rancho Blanco Road Project from Alamo to Tower Road. C-12-314-01-29.
BACKGROUND
Supplemental Agreement is being processed since the construction contract approved by Commissioner Court on 1/14/14 AI#42514 came in higher than the engineers original estimate. The engineers original estimate was $193,145 and the construction contract was approved at $297,936.13.
Fiscal Impact
- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1200-431-00-122-086-0-731
- FUNDS AVAILABLE Y/N?:
- Y/Pending
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding pending approval of AI#43613 CC 3/18/14.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/14/2014 04:04 PM |
| Budget and Management | Debbie Tamez | 03/14/2014 04:05 PM |
| Auditor's Office | Monica Salinas | 03/14/2014 05:08 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 03/14/2014 03:22 PM
- Final Approval Date:
- 03/14/2014