CAPTION
Requesting approval of Supplemental Agreement No. 3 to Work Authorization No. 1 (a decrease of $ 86,900.00) in connection to contract # C-11-234-09-13 with L&G Consulting Engineering, Inc. for the (Job Specific) Project: "FM 1925-from Kenyon Road to FM 907 (Alamo Road)" for Hidalgo County Precinct No. 4.
BACKGROUND
Supplemental Agreement#3 to WA#1 - L&G Engineering - C-11-234-09-13
Fiscal Impact
- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1342-431-00-124-076-0-841
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?: