AI- 46160
Executive Office 6.B.
CC CONSENT
- Meeting Date:
- 09/09/2014
- Submitted By:
- Rebecca Gomez, EXECUTIVE OFFICE
- Department:
- EXECUTIVE OFFICE
Information
CAPTION
Right of Way:
Agua Special Utility District (AGUA SUD):
* This proposed installation includes approximately 1,813 linear feet of 12-inch diameter PVC waterline along the south right-of-way of Mile 3 North Road and ending at the northeast corner of Mile 3 North Road and Abram Road. This installation also includes multiple elbows (mech. joint), gate valves, air release valves, and 169 linear feet of 22" diameter steel casing (by bore). The existing will not be open-cut; all waterline proposed under the roadway pavement will be installed by bore and jack, and encased within a steel casing.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Debbie Tamez | 08/29/2014 03:50 PM |
| Auditor's Office | Monica Salinas | 09/05/2014 05:45 PM |
- Form Started By:
- Rebecca Gomez
- Started On:
- 08/22/2014 02:50 PM
- Final Approval Date:
- 09/05/2014