CAPTION
Acceptance and approval of Change Order No. 3 for an extension of sixty (60) additional days, epoxy flooring, metal soffit at porch, electric door strike in the total amount of $32,900.00 to Contract No. C-13-072A-11-19 with Couric Enterprises, LLC dba Foremost Construction as reviewed/approved by project architect of record, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of a Community Resource Center in San Carlos" with authority for County Judge, or Court Member to execute document.
BACKGROUND
CHANGE ORDER #2 - FOREMOST CONSTRUCTION
Fiscal Impact
- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1342-419-40-124-123-0-720
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funds available as of 11/26/14.Original P.O. # 703489 will be increased.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 11/25/2014 04:30 PM |
| Budget and Management | Debbie Tamez | 11/26/2014 09:26 AM |
| Auditor's Office | Monica Salinas | 11/26/2014 03:59 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/25/2014
- Final Approval Date:
- 11/26/2014